Project Description:
BEDFORD- IMPROVEMENTS AT JOHN GLENN MIDDLE (SRTS)
The project includes the signalization of Mudge Way / Great Road and reconstruction of sidewalk along Great Road and Mudge Way and installation of crosswalks across Mudge Way, construction of sidewalk along Mudge Way at the Bedford High School driveway to connect with an existing path to Railroad Avenue and John Glenn Middle School. These improvements will include the installation of ADA compliant wheelchair ramps, installation of MUTCD compliant signs and pavement markings and minor drainage improvements.
Location:
  • Town of Bedford
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Michael Bartolo
    Construction Bid Price: $1,103,443.00
    District: District 4

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final
    # 97281 -- Construction Contract
    Multi-Use Path Construction (Including Signals) along a Section of Mudge Way and Adjacent Streets (Safe Routes to School – John Glenn Middle School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/06/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2014
    Project Initiation Form PIF Entered 10/27/2014
    Project Initiation Form PIF Entered 07/01/2015
    Project Initiation Form PIF Entered 07/10/2015
    Project Initiation Form PRC Submitted 10/27/2014
    Project Review Committee PRC Tabled 11/06/2014
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 08/20/2016
    Project Management
    100% Design 100% Package Received 04/12/2016
    100% Design 100% Package Comments to DE 05/24/2016
    25% Design 25% Package Received 10/30/2015
    25% Design 25% Package Comments to DE 01/08/2016
    25% Design Design Public Hearing 02/11/2016
    75% Design 75% Package Received 10/30/2015
    75% Design 75% Package Comments to DE 01/08/2016
    Final Design PS&E Received 08/09/2016
    Final Design PS&E Received 08/16/2016
    Final Design PS&E to FAPRO 08/15/2016