Project Description:
LAWRENCE- IMPROVEMENTS AT BRUCE ELEMENTARY SCHOOL (SRTS)
The project includes constructing curb bump-outs with a landscaped buffer on Haverhill Street at the intersection with Milton Street. The curb bump outs will shorten crossings distances and reduce curb radii and vehicle turning speeds. The project also includes reconstructing 6-8’ wide sidewalks with granite curb along both sides of Milton Street between Haverhill Street and Lowell Street. Curb bump-outs and new ADA compliant wheelchair ramps will be provided along Milton Street at the intersections of Butler Street and Providence Street. Other improvements include removing the channelized right-turn lane from Lowell Street westbound to Milton Street northbound to reduce vehicle speeds and lane encroachment along Milton Street and providing a pavement mill and overlay within the limits of the project. These improvements will include the installation of ADA-compliant wheelchair ramps, installation of MUTCD-compliant signs and pavement markings, and minor drainage improvements.
Location:
  • City of Lawrence
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Lokman Arran
    Construction Bid Price: $1,727,000.00
    District: District 4

    Contracts (2) Progress
    # 100843 -- Construction Contract
    Pedestrian and Bicycle Improvements and Related Work at the Intersection of Butler and Milton Streets and Adjacent Streets (Safe Routes to School – Alexander B. Bruce School). Completed
    # 85766 -- Design -- Highway
    Work will consist of providing school assessments and preliminary and final engineering design and construction phase services to the Highway Engineering Division for the 2014 Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/25/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2014
    Project Initiation Form PIF Entered 10/29/2014
    Project Initiation Form PIF Entered 11/23/2015
    Project Initiation Form PIF Entered 11/25/2015
    Project Initiation Form PIF Entered 11/25/2015
    Project Initiation Form PRC Submitted 10/29/2014
    Project Initiation Form PRC Submitted 11/25/2015
    Project Initiation Form PRC Submitted 11/25/2015
    Project Review Committee PRC Tabled 11/06/2014
    Project Review Committee PRC Tabled 06/25/2015
    Project Review Committee PRC Approved 11/23/2015
    Project Status Advertised 06/24/2017
    Project Management
    100% Design 100% Package Received 10/05/2016
    100% Design 100% Package Comments to DE 11/23/2016
    25% Design 25% Package Comments to DE 05/26/2016
    25% Design Design Public Hearing 08/24/2016
    75% Design 75% Package Received 03/08/2016
    75% Design 75% Package Comments to DE 05/12/2016
    Final Design PS&E Received 03/17/2017
    Final Design PS&E Received - Resub 2 05/05/2017