WEYMOUTH- IMPROVEMENTS AT PINGREE ELEMENTARY SCHOOL (SRTS)
include mill and overlay along Commercial Street from 500 ft n of Cottage Street to about 350 ft s of the school driveway. Pedestrian improvements will include wheelchair ramp and sidewalk reconstruction to meet ADA requirements. The curb bump out will narrow the roadway and reduce crossing distance. Share the road signs will be constructed
Location:
  • Town of Weymouth
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Edward Moschella Jr
    Construction Bid Price: $409,900.00
    District: District 6

    Contracts (2) Progress
    # 102061 -- Construction Contract
    Pedestrian Improvements and Related Work at the Intersections of Pingree School Driveway, Cottage and Commercial Streets (Safe Routes to School – Pingree Elementary School). Completed
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/27/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2014
    Project Initiation Form PIF Entered 11/03/2014
    Project Initiation Form PIF Entered 11/25/2015
    Project Initiation Form PRC Submitted 11/03/2014
    Project Initiation Form PRC Submitted 11/25/2015
    Project Review Committee PRC Tabled 06/25/2015
    Project Review Committee PRC Approved 02/11/2016
    Project Status Advertised 08/26/2017
    Project Management
    100% Design 100% Package Received 05/09/2017
    100% Design 100% Package Comments to DE 06/23/2017
    25% Design 25% Package Received 12/01/2016
    25% Design Design Public Hearing 03/02/2017
    75% Design 75% Package Received 12/01/2016
    75% Design 75% Package Comments to DE 02/02/2017
    Final Design PS&E Received 07/03/2017
    Final Design Peer Review Comments to DE 06/26/2017
    Final Design PS&E to FAPRO 08/14/2017