| Project Description: |
FRAMINGHAM- PEDESTRIAN HYBRID BEACON INSTALLATION AT ROUTE 9 AND MAYNARD ROAD
The proposed project will construct an at-grade pedestrian crossing across Route 9 in the vicinity of Maynard Road and the Framingham Fire Station. The crossing will be controlled by a pedestrian hybrid beacon (HAWK signal). The project also includes the reconstruction of the existing emergency signal for the Framingham Fire Station on Route 9.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Muazzez G Reardon![]() |
| Estimated Total Contract Cost: | $730,117.10 |
| Estimated Total Federal Participating Construction Cost: | $904,775.25 |
| District: | District 3 |
| Current Status: | Design Public Hearing (as of 06/28/2017 ) |
|
Bridges |
||||||||||||||
|
|
|
|||||||||||||||||||||||||||||