Project Description:
COHASSET- SCITUATE- CORRIDOR IMPROVEMENTS AND RELATED WORK ON JUSTICE CUSHING HIGHWAY (ROUTE 3A), FROM BEECHWOOD STREET TO HENRY TURNER BAILEY ROAD
Work on this project includes corridor improvements from the Beechwood Street intersection to the Cohasset/Scituate Town Line. The Route 3A/Beechwood Street intersection will be upgraded with new traffic signal equipment as well as minor geometric improvements. The Route 3A/Henry Turner Bailey Road intersect ion will be signalized as well as geometric improvements. Pedestrian and bicycle accommodation will be included along the corridor.
Location:
  • Town of Cohasset
  • Town of Scituate
  • Construction Begins: Winter 2024/2025
    Resident Engineer: Charles Young
    Construction Bid Price: $17,679,256.90
    District: District 5
    Current Status: Current Operations: Survey / signage / erosion control Future Operations: Drainage/Clearing , grubbing Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/09/2025)

    Contracts (2) Progress
    # 127970 -- Construction Contract
    Corridor Improvements and Related Work on Justice Cushing Highway (Route 3A), from Beechwood Street To Henry Turner Bailey Road 4% Complete
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/06/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Current Operations: Survey / signage / erosion control Future Operations: Drainage/Clearing , grubbing Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/03/2014
    Project Initiation Form PIF Entered 06/25/2014
    Project Initiation Form PRC Submitted 06/25/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 08/31/2024
    Project Management
    100% Design 100% Package Received 06/06/2022
    100% Design 100% Package Comments to DE 08/19/2022
    100% Design 100% Package Received - Resub 1 02/23/2024
    100% Design 100% Package Received - Resub 2 05/17/2024
    100% Design 100% Plans Approved 09/22/2022
    100% Design 100% Plans Complete 09/22/2022
    25% Design 25% Package Received 04/19/2017
    25% Design 25% Package Comments to DE 12/04/2017
    25% Design Design Public Hearing 03/03/2020
    75% Design 75% Package Received 02/10/2021
    Final Design PS&E Received 05/29/2024
    Final Design PS&E to FAPRO 08/19/2024
    Final Design PS&E Received - Resub 1 08/19/2024