BOXBOROUGH- BRIDGE REPLACEMENT, B-18-002, ROUTE 111 OVER I-495
The existing bridge was built in 1963 and is now structurally deficient (4-6-5). It consists of 5 simple spans with two abutments and three piers. It is proposed to replace the bridge with an integral abutment two span continuous structure. It is also proposed to increase the existing vertical clearance from 15 feet to 16.5 feet. The existing curb to curb width is 48 feet. The four travel lanes are 11 feet wide which only provides for two - 2 foot shoulders. There are no sidewalks. At a minimum the bridge needs to be widened to provide 5 foot shoulders for bicycle accomodation. It has not yet been determined if there is a need for one or two sidewalks.
Location:
  • Town of Boxborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2023/2024
    Project Manager: Ashish Patel
    Estimated Total Contract Cost: $28,763,142.30
    Estimated Total Federal Participating Construction Cost: $31,320,796.95
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 09/09/2023 )

    Contracts (1) Progress
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/05/2014
    Project Initiation Form PIF Entered 06/05/2014
    Project Initiation Form PRC Submitted 06/05/2014
    Project Review Committee PRC Approved 11/18/2014
    Project Status Advertised 09/09/2023
    Project Management
    100% Design 100% Package Received 08/09/2023
    25% Design 25% Package Received 05/12/2022
    25% Design 25% Package Received - Resub 1 04/04/2023
    Final Design PS&E to FAPRO 08/30/2023
    Consultant Contract Process Workhours Approved 08/15/2017