BOSTON- RAMP COVERINGS FOR ROSE KENNEDY GREENWAY ON PARCELS 6, 12 & 18 (DESIGN)
This project involves the CA/T mitigation commitment to cover the ramps at parcels 6,12 and 18. Parcel No. 6 Plannedf surface pedestrian connections from N. Washington St southerly to Subury St at Haymarket Parcel 12 Ramp Cover and Pedestrian Access Project (Dock Sq) Design and Consruction of CA/T Ramp Portal Cover System over portions of Ramps CS-SA and Cn-SA on RKG, Planned surface pedestrian connection from N St southerly to Clinton St at Armenian Heritage Park Boston Parcel 18 Ramp Cover Project (Rowes Wharf) Planned improvements includine landscaping and screening elements form High Street southerly to Oliver St
Location:
  • City of Boston
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $42,693,750.00
    Estimated Total Federal Participating Construction Cost: N/A
    Current Status: This project is in the preliminary design phase.

    Contracts (5) Progress
    # 68387 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77866 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77871 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/13/2014
    Project Initiation Form PIF Entered 06/13/2014
    Project Initiation Form PRC Submitted 05/07/2015
    Project Review Committee PRC Approved 06/25/2015