Project Description:
QUINCY- INTERSECTION IMPROVEMENTS @ SEA STREET & QUINCY SHORE DRIVE
This project involves intersection improvements at the intersection of Quincy Shore Drive, which is a DCR roadway, and Sea Street. The intersection of Quincy Shore Drive is expansive.
Location:
  • City of Quincy
  • Construction Begins: Spring 2019
    Resident Engineer: Kevin Laramee
    Construction Bid Price: $2,471,055.00
    District: District 6

    Contracts (4) Progress
    # 105939 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Sea Street and Quincy Shore Road Completed
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77889 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/15/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/18/2014
    Project Initiation Form PIF Entered 06/18/2014
    Project Initiation Form PRC Submitted 07/09/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 06/18/2018
    25% Design 25% Package Received 04/27/2016
    25% Design 25% Package Comments to DE 08/03/2016
    25% Design Design Public Hearing 11/16/2016
    75% Design 75% Package Received 10/23/2017
    75% Design 75% Package Comments to DE 02/14/2018
    Final Design PS&E Received 08/17/2018
    Final Design PS&E to FAPRO 08/23/2018