Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BRIMFIELD- STURBRIDGE- RESURFACING & RELATED WORK ON ROUTE 20, BEGINNING EAST OF NEW HOLLAND ROAD (MM 87.8), ENDING WEST OF GALILEO DRIVE (MM 91.9)
The project will consist of milling and resurfacing Route 20 in Brimfield and Sturbridge, beginning just east of New Holland Road in Brimfield and continuing easterly, ending just west of Galileo Drive in Sturbridge for a total length of 4.06 miles. This project will also include adjusting and/or rebuilding drainage structures, resetting highway guardrail, installing milled rumble strips at shoulders, durable wet reflective recessed pavement markings, slotted pavement markers, proposed signage, solar powered driver feedback sign, two lane classification traffic data station, HMA berm and curb, safety controls, erosion-sedimentation control measures, and other incidental items.
Location:
  • Town of Brimfield
  • Town of Sturbridge
  • Construction Begins: Autumn 2016
    Resident Engineer: Richard Wonderlie
    Construction Bid Price: $2,668,192.25
    District: District 2

    Contracts (1) Progress
    # 94661 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 20 (Sturbridge Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/29/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/27/2014
    Project Initiation Form PIF Entered 06/27/2014
    Project Initiation Form PRC Submitted 07/02/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 05/28/2016
    Project Management
    100% Design 100% Package Received 01/07/2016
    25% Design 25% Package Received 05/26/2015
    25% Design 25% Package Comments to DE 06/23/2015
    25% Design Design Public Hearing 02/09/2016
    75% Design 75% Package Received 05/26/2015
    75% Design 75% Package Comments to DE 06/23/2015
    Final Design PS&E Received 01/07/2016
    Final Design PS&E Received 05/17/2016
    Final Design PS&E to FAPRO 05/23/2016