Project Description:
HAVERHILL- BRADFORD RAIL TRAIL EXTENSION, FROM ROUTE 125 TO RAILROAD STREET
The project will extend the Bradford rail trail approximately 1100 feet from the Route 125 (Basiliere Bridge) to Railroad Street. The project will include construction of a 10 foot wide path with 2 foot shoulders, vegetation clearing, drainage and paving. The timber decking on a small rail road bridge will be replaced and railings added to accommodate bicycles and pedestrians. the project will also include pedestrian lighting, signs, fencing and landscaping. The project is envisioned to utilize the existing Route 125 underpass. Coordination with any proposed work by MassDOT on this structure will be required.
Location:
  • City of Haverhill
  • Construction Begins: Autumn 2020
    Resident Engineer: Fred Collins
    Construction Bid Price: $1,309,816.50
    District: District 4

    Contracts (1) Progress
    # 112232 -- Construction Contract
    Construction of the Bradford Rail Trail Extension from Route 125 to Railroad Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/23/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/02/2014
    Project Initiation Form PIF Entered 12/08/2014
    Project Initiation Form PRC Submitted 02/18/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 07/25/2020
    Project Management
    100% Design 100% Package Received 01/16/2020
    100% Design 100% Package Comments to DE 02/18/2020
    25% Design 25% Package Received 12/15/2017
    25% Design 25% Package Comments to DE 06/13/2018
    25% Design Design Public Hearing 01/16/2019
    75% Design 75% Package Received 09/20/2019
    75% Design 75% Package Comments to DE 11/01/2019
    Final Design PS&E Received 06/18/2020
    Final Design PS&E to FAPRO 07/13/2020