Project Description:
NEWBURYPORT- INTERSECTION IMPROVEMENTS @ ROUTE 1 & MERRIMAC STREET
The project will install traffic control signals at the intersection of the Route 1 northbound and southbound ramps and Merrimac Street. Sidewalk, crosswalk and bicycle accommodations will be included.
Location:
  • City of Newburyport
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Misrak Sultan
    Estimated Total Contract Cost: $2,301,200.00
    Estimated Total Federal Participating Construction Cost: $2,474,580.00
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/02/2014
    Project Initiation Form PIF Entered 07/02/2014
    Project Initiation Form PRC Submitted 07/03/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Management