Project Description:
AUBURN, FITCHBURG & MARLBOROUGH - FAP # HSI-002S(751)X - HIGH FRICTION SURFACE TREATMENT, PAVEMENT REPAIRS AND RELATED WORK ALONG SECTIONS OF ROUTE 2, INTERSTATES 290 AND 495. (608032)
This project consists of installing a high friction surface treatment on the ramp in Auburn from I-290 Eastbound to Route 12 Southbound, a section of Route 2 in Fitchburg, and on the ramp in Marlborough from I-290 Eastbound to I-495 Northbound.
Location:
  • Town of Auburn
  • City of Fitchburg
  • City of Marlborough
  • Resident Engineer: Stephen Romano
    Construction Contract Value: $2,887,603.50
    Construction Bid Price: $2,486,185.00
    Initial Construction Estimate: $2,075,000.00
    District: District 3

    Contracts (1) Progress
    # 84984 -- Construction Contract
    High Friction Surface Treatment Pavement Repairs and Related Work along Sections of Route 2, Interstates 290 and 495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/17/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/07/2014
    Project Initiation Form PIF Entered 08/01/2014
    Project Initiation Form PRC Submitted 08/01/2014
    Project Review Committee PRC Approved 08/21/2014
    Project Status Advertised 09/13/2014
    Project Management
    Final Design PS&E Received 08/29/2014
    Final Design PS&E to FAPRO 09/10/2014