WESTFORD- INTERSECTION IMPROVEMENTS @ GROTON ROAD (ROUTE 40) & OAK HILL ROAD, INCLUDES NEW BRIDGE W-26-027
Proposed Improvements include new sidewalks, minor roadway widening, pavement resurfacing, a new traffic signal at the intersection of Route 40 and Oak Hill Road, and reconstruction of the culvert that conveys Gilson Brook under Route 40.
Location:
  • Town of Westford
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Arvind Patel
    Construction Bid Price: $2,446,674.16
    District: District 3

    Contracts (1) Progress
    # 100546 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals and Pre-Cast Culvert Br. No. W-26-027) Groton Road (Route 40) at Oak Hill Road. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/18/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/14/2014
    Project Initiation Form PIF Entered 07/21/2014
    Project Initiation Form PRC Submitted 07/21/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 05/27/2017
    Project Management
    100% Design 100% Package Received 02/14/2017
    100% Design 100% Package Comments to DE 03/10/2017
    25% Design 25% Package Received 05/11/2015
    25% Design 25% Package Comments to DE 09/04/2015
    25% Design 25% Package Received - Resub 1 06/27/2016
    25% Design Design Public Hearing 10/04/2016
    75% Design 75% Package Received 11/15/2016
    75% Design 75% Package Comments to DE 12/20/2016
    Final Design PS&E Received 04/11/2017
    Final Design PS&E to Peer Reviewer 02/21/2017
    Final Design Peer Review Comments to DE 03/10/2017
    Final Design PS&E to FAPRO 05/04/2017