Project Description:
WESTFORD- INTERSECTION IMPROVEMENTS @ GROTON ROAD (ROUTE 40) & DUNSTABLE ROAD
Proposed improvements will include the installation of a fully-actuated traffic signal at the intersection, resurfacing with box widening, bicycle lanes, sidewalks, drainage updates and geometric improvements.
Location:
  • Town of Westford
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Arvind Patel
    Construction Bid Price: $2,728,823.67
    District: District 3

    Contracts (1) Progress
    # 105481 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Groton (Route 40) and Dunstable Roads Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/16/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/14/2014
    Project Initiation Form PIF Entered 07/21/2014
    Project Initiation Form PRC Submitted 07/21/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 08/11/2018
    Project Management
    25% Design 25% Package Received 02/17/2017
    25% Design 25% Package Comments to DE 05/03/2017
    25% Design 25% Package Received - Resub 1 06/27/2017
    25% Design Design Public Hearing 10/19/2017
    75% Design 75% Package Received 11/28/2017
    75% Design 75% Package Comments to DE 01/10/2018
    Final Design PS&E Received 05/10/2018
    Final Design Peer Review Comments to DE 06/13/2018
    Final Design PS&E to FAPRO 07/23/2018
    Final Design PS&E Received - Resub 1 10/15/2018