Project Description:
WEBSTER- RESURFACING & RELATED WORK OF KLEBART AVENUE & LAKE PARKWAY
Proposed improvements to Klebart Avenue and Lake Parkway will include reconstruction of existing roadway, new sidewalks and bicycle lanes.
Location:
  • Town of Webster
  • Construction Begins: Summer 2020
    Resident Engineer: Thomas Donnelly
    Construction Bid Price: $4,754,484.00
    District: District 3

    Contracts (1) Progress
    # 110500 -- Construction Contract
    Resurfacing and Related Work on a Section of Klebart Avenue and Lake Parkway Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/01/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/14/2014
    Project Initiation Form PIF Entered 07/21/2014
    Project Initiation Form PRC Submitted 07/21/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 12/28/2019
    Project Management
    100% Design 100% Package Received 03/13/2019
    100% Design 100% Package Comments to DE 06/24/2019
    25% Design 25% Package Received 08/10/2015
    25% Design 25% Package Comments to DE 12/03/2015
    25% Design Design Public Hearing 04/25/2017
    75% Design 75% Package Received 12/26/2017
    Final Design PS&E Received 09/13/2019
    Final Design PS&E Received - Resub 1 11/01/2019
    Final Design PS&E Received - Resub 2 12/13/2019