BOYLSTON- WEST BOYLSTON- STORMWATER IMPROVEMENTS ON ROUTE 140 AT THE WACHUSETT RESERVOIR SOUTH BAY
The proposed project involves drainage improvements along Route 140 in the Town of West Boylston. The goal of the project is to provide stormwater mitigation for direct discharges to the Wachusett Reservoir South Bay.
Location:
  • Town of Boylston
  • Town of West Boylston
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Michael Chauvin
    Construction Bid Price: $3,604,719.64
    District: District 3

    Contracts (1) Progress
    # 97682 -- Construction Contract
    Water Main and Drainage Improvements and Related Work on Sections of Route 140 (Beaman and Temple Streets). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/08/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/23/2014
    Project Initiation Form PIF Entered 07/23/2014
    Project Initiation Form PRC Submitted 07/23/2014
    Project Review Committee PRC Approved 08/01/2014
    Project Status Advertised 09/03/2016
    Project Management
    100% Design 100% Package Received 07/19/2016
    25% Design 25% Package Received 12/23/2014
    25% Design 25% Package Comments to DE 05/26/2015
    25% Design Design Public Hearing 05/02/2016
    75% Design 75% Package Received 07/19/2016
    Final Design PS&E Received 08/16/2016
    Final Design PS&E to Peer Reviewer 08/16/2016
    Final Design Peer Review Comments to DE 08/19/2016
    Final Design PS&E Received - Resub 1 08/26/2016