Project Description:
FALL RIVER- CORRIDOR IMPROVEMENTS ON ROUTE 79/DAVOL STREET
Work on this project consists of preliminary design and environmental permitting as described in the Fall River Route 79/Davol Street Study completed in 2014.
Location:
  • City of Fall River
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2022
    Project Manager: Valerie E Kilduff
    Estimated Total Contract Cost: $125,302,755.32
    Estimated Total Federal Participating Construction Cost: $119,427,595.11
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 03/26/2022 )

    Contracts (3) Progress
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77875 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 80660 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/19/2014
    Project Initiation Form PIF Entered 08/19/2014
    Project Initiation Form PRC Submitted 10/29/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 03/26/2022
    Project Management
    100% Design 100% Package Received 02/23/2022
    25% Design 25% Package Received 08/03/2021
    25% Design 25% Package Comments to DE 09/08/2021
    25% Design 25% Package Received - Resub 1 01/04/2022
    25% Design 25% Package Received - Resub 2 02/22/2022
    25% Design Design Public Hearing 10/27/2021
    Final Design PS&E to FAPRO 03/21/2022