NORWOOD- INTERSECTION & SIGNAL IMPROVEMENTS AT US 1 (PROVIDENCE HIGHWAY) & MORSE STREET
Work will consist of improving the intersection and signals at US Route 1 (Providence Highway) and Morse Street.
Location:
  • Town of Norwood
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2028
    Project Manager: Aidee Cira
    Estimated Total Contract Cost: $10,176,107.38
    Estimated Total Federal Participating Construction Cost: $12,578,369.50
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Received - Resub 1 (as of 09/11/2024 )

    Contracts (2) Progress
    # 115784 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77875 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NORWOOD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,501,200.90
    State Cost: $166,800.10
    Total Cost: $1,668,001.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/29/2014
    Project Initiation Form PIF Entered 08/29/2014
    Project Initiation Form PRC Submitted 08/29/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Management
    25% Design 25% Package Received 11/16/2018
    25% Design 25% Package Received 09/10/2024
    25% Design 25% Package Received - Resub 1 09/11/2024
    Consultant Contract Process NTP Issued 11/16/2022