Project Description:
MANSFIELD- INTERSECTION & SIGNAL IMPROVEMENTS AT SR 140 (COMMERCIAL STREET) & SR 106 (CHAUNCEY STREET)
Work will consist of improving the intersection and signals at SR 140 (Commercial Street) and SR 106 (Chauncey Street).
Location:
  • Town of Mansfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2024
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $1,316,587.50
    Estimated Total Federal Participating Construction Cost: $1,499,312.50
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: 25% Package Comments to DE (as of 04/05/2019 )

    Contracts (1) Progress
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: MANSFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,511,307.90
    State Cost: $167,923.10
    Total Cost: $1,679,231.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/29/2014
    Project Initiation Form PIF Entered 08/29/2014
    Project Initiation Form PRC Submitted 08/29/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Management
    25% Design 25% Package Received 01/24/2019
    25% Design 25% Package Comments to DE 04/05/2019