Project Description:
BOSTON- GRADE SEPARATED MULTI-USE PATH CONSTRUCTION ALONG THE PAUL DUDLEY WHITE PATH AT NORTH HARVARD STREET BRIDGE OVER CHARLES RIVER (ANDERSON MEMORIAL BRIDGE)
This project involves the construction of a grade spearated Multi-Use path at North Harvard Street Bridge over Charles River (Anderson Memorial Bridge) for the Paul Dudley White Bike Path. This is a seperate MassDOT project related to the Anderson Memorial Bridge Replacement (Project Number 605517).
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Michael Trepanier
    Estimated Total Contract Cost: $5,142,310.53
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: 25% Package Received (as of 03/07/2015 )

    Contracts (1) Progress
    # 77862 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/03/2014
    Project Initiation Form PIF Entered 09/03/2014
    Project Initiation Form PRC Submitted 09/03/2014
    Project Review Committee PRC Approved 09/09/2014
    Project Management
    25% Design 25% Package Received 03/07/2015
    Consultant Contract Process NTP Issued 11/09/2014