Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORCESTER- STORMWATER IMPROVEMENTS ALONG I-290 AND 122A
Location:
  • City of Worcester
  • Construction Begins: Summer 2020
    Resident Engineer: Dariusz Wisniewski
    Construction Bid Price: $1,720,845.00
    District: District 3

    Contracts (2) Progress
    # 111595 -- Construction Contract
    Stormwater Improvements and Related Work along a Section of Interstate 290 Completed
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/03/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/09/2014
    Project Initiation Form PIF Entered 09/09/2014
    Project Initiation Form PRC Submitted 09/09/2014
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 06/13/2020
    Project Management
    100% Design 100% Package Received 02/20/2020
    100% Design 100% Package Comments to DE 04/03/2020
    25% Design 25% Package Received 08/30/2019
    75% Design 75% Package Received 02/20/2020
    Final Design PS&E Received 05/20/2020
    Final Design PS&E to FAPRO 06/05/2020