Project Description:
GARDNER- SHREWSBURY- STORMWATER IMPROVEMENTS ALONG ROUTE 68 AND ROUTE 70
Work consists of improving stormwater along Route 68 and Route 70
Location:
  • City of Gardner
  • Town of Shrewsbury
  • Construction Begins: Spring 2016
    Resident Engineer: Ryan Davison
    Construction Bid Price: $535,073.70
    District: District 3

    Contracts (1) Progress
    # 92531 -- Construction Contract
    Drainage Improvements along a Section of Routes 68 (West Street) and 70 (Clinton Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/05/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/09/2014
    Project Initiation Form PIF Entered 09/11/2014
    Project Initiation Form PRC Submitted 01/02/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 12/26/2015
    Project Management
    100% Design 100% Package Received 07/20/2015
    100% Design 100% Package Comments to DE 10/27/2015
    25% Design 25% Package Received 03/02/2015
    25% Design 25% Package Comments to DE 06/23/2015
    Final Design PS&E Received 12/04/2015
    Final Design PS&E to Peer Reviewer 12/04/2015
    Final Design PS&E to FAPRO 12/21/2015