Project Description:
WOBURN- BURLINGTON- INTERSECTION RECONSTRUCTION AT ROUTE 3 (CAMBRIDGE ROAD) & BEDFORD ROAD AND SOUTH BEDFORD STREET
The project will reconstruction the intersection of Route 3 and Bedford Road in Woburn. The project includes added left turn lanes, accommodations for bicycles and pedestrians and new traffic signals.
Location:
  • Town of Burlington
  • City of Woburn
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2027
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $5,615,915.00
    Estimated Total Federal Participating Construction Cost: $7,266,714.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 100% Package Received (as of 09/10/2026 )

    Contracts (1) Progress
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BURLINGTON
    WOBURN
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $5,551,344.90
    State Cost: $616,816.10
    Total Cost: $6,168,161.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/29/2014
    Project Initiation Form PIF Entered 09/29/2014
    Project Initiation Form PRC Submitted 09/29/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Management
    100% Design 100% Package Received 09/10/2026
    25% Design 25% Package Received 11/17/2023
    25% Design 25% Package Comments to DE 12/27/2023
    25% Design 25% Package Approved 01/22/2024
    25% Design Design Public Hearing 03/27/2024
    75% Design 75% Package Received 11/17/2025