BOSTON- RECONSTRUCTION OF SOUTH BANK PARK
This narrow strip of land along the top of the dam between DSB locks and Lovejoy Wharf is an integral part of the CA/T Project’s New Charles River Basin Parks (“NCRBP”) 42-acre mitigation commitment. MassDOT transferred to DCR certain property interests in Cambridge parcels within the New Charles River Basin Parks (“NCRBP”) in late September 2014, in keeping with outstanding CA/T Project commitments. MassDOT is completing negotiations with DCR to transfer the remaining NCRBP property interests, located in Boston, which includes an unfinished triangular park parcel on the New Charles River Dam South Bank. In 2013 MassDOT confirmed that it remained committed to completing design, construction, & funding of the Dam South Bank parkland (“DSB”), which had to be removed at the last minute from the North Bank Bridge (“NBB”) (formerly CA/T Project C29F1) contract bid package in July 2009 to allow that ARRA project to move forward. parkland, access to I-93 and dam infrastructure for operations & maintenance, and DCR/police vehicular and boat parking/storage.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $690,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/07/2014
    Project Initiation Form PIF Entered 10/07/2014
    Project Initiation Form PRC Submitted 10/07/2014
    Project Review Committee PRC Approved 11/06/2014