Project Description:
WESTFIELD- WESTFIELD RIVER LEVEE MULTI-USE PATH CONSTRUCTION, FROM ELLSWORTH STREET TO WILLIAMS RIDING WAY (NEAR MEADOW STREET) (2 MILES)
Location:
  • City of Westfield
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2023/2024
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $5,088,004.78
    Estimated Total Federal Participating Construction Cost: $5,134,193.39
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: PS&E Received (as of 01/11/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTFIELD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $4,148,097.60
    State Cost: $1,037,024.40
    Total Cost: $5,185,122.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/09/2014
    Project Initiation Form PIF Entered 10/09/2014
    Project Initiation Form PRC Submitted 10/22/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Management
    100% Design 100% Package Received 08/12/2022
    100% Design 100% Package Comments to DE 09/14/2022
    100% Design 100% Plans Approved 12/07/2022
    100% Design 100% Plans Complete 12/07/2022
    25% Design 25% Package Received 05/15/2019
    25% Design 25% Package Comments to DE 08/14/2019
    25% Design Design Public Hearing 08/19/2020
    75% Design 75% Package Received 12/29/2020
    75% Design 75% Package Comments to DE 04/05/2021
    75% Design 75% Plans Approved 08/16/2021
    75% Design 75% Plans Complete 08/16/2021
    Final Design PS&E Received 01/11/2023