Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- REMOVAL AND REPLACEMENT OF THE TED WILLIAMS TUNNEL CEILING SYSTEM (CRC 14A - DESIGN ONLY)
Removal and replacement of the ceiling system will include the fastening systems, air flow calculations, and material selection. Project may also include fire and heat sensors, fire protection systems, communication and other system to be relocated.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $46,000,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/15/2014
    Project Initiation Form PIF Entered 10/15/2014
    Project Initiation Form PIF Entered 11/25/2015
    Project Initiation Form PRC Submitted 10/15/2014
    Project Initiation Form PRC Submitted 11/25/2015
    Project Review Committee PRC Tabled 11/06/2014
    Project Review Committee PRC Approved 02/11/2016
    Project Management