Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHELSEA- RECONSTRUCTION ON BROADWAY (ROUTE 107), FROM CITY HALL AVENUE TO THE REVERE C.L.
This project involves the reconstruction of one mile of Broadway. Improvements tot he roadway will include surface and subsurface work include replacement of utilities. Construction of a dedicate bike lane along Broadway. Upgrades to the existing sidewalk network including ADA compliant ramps at all intersections.
Location:
  • City of Chelsea
  • Construction Begins: Spring 2022
    Resident Engineer: Mauricio Morales
    Construction Bid Price: $11,578,804.00
    District: District 6

    Contracts (1) Progress
    # 117601 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Broadway (Route 107) 45% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/16/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/21/2014
    Project Initiation Form PIF Entered 10/21/2014
    Project Initiation Form PIF Entered 07/10/2015
    Project Initiation Form PRC Submitted 10/21/2014
    Project Review Committee PRC Tabled 11/06/2014
    Project Review Committee PRC Approved 06/25/2015
    Project Status Advertised 03/19/2022
    Project Management
    100% Design 100% Package Received 05/14/2021
    100% Design 100% Package Comments to DE 07/23/2021
    25% Design 25% Package Received 04/14/2017
    25% Design 25% Package Comments to DE 09/26/2017
    25% Design Design Public Hearing 03/21/2019
    75% Design 75% Package Received 07/09/2020
    75% Design 75% Package Comments to DE 10/15/2020
    Final Design PS&E Received 11/24/2021
    Final Design PS&E Received - Resub 1 01/14/2022