Project Description:
SHARON- BRIDGE REPLACEMENT, S-09-003 (40N), MASKWONICUT STREET OVER AMTRAK/MBTA
Work on this project shall consist of replacing the bridge that is currently closed due to deterioration.
Location:
  • Town of Sharon
  • Construction Begins: Autumn 2021
    Resident Engineer: Charles Young
    Construction Bid Price: $7,257,552.00
    District: District 5
    Current Status: Current Operations: Project is currently idle. Future Operations: Utility work by Verizon once Amtrak assistance can be obtained. Amtrak to Install temporary catenary Normal work hours are Monday through Friday 7:00 Am to 3:30 PM. Expect periodic lane closures and restrictions. (as of 03/05/2024)

    Contracts (4) Progress
    # 114943 -- Construction Contract
    Bridge Replacement Br. No. S-09-003 (Steel) Maskwonicut Street over the Amtrak/MBTA Railroad 9% Complete
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77888 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/14/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Current Operations: Project is currently idle. Future Operations: Utility work by Verizon once Amtrak assistance can be obtained. Amtrak to Install temporary catenary Normal work hours are Monday through Friday 7:00 Am to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/21/2014
    Project Initiation Form PIF Entered 10/21/2014
    Project Initiation Form PRC Submitted 10/22/2014
    Project Review Committee PRC Approved 11/18/2014
    Project Status Advertised 06/26/2021
    Project Management
    100% Design 100% Package Received 08/19/2020
    100% Design 100% Package Rejected 10/19/2020
    100% Design 100% Package Received - Resub 1 12/18/2020
    100% Design 100% Package Received - Resub 2 03/12/2021
    100% Design 100% Plans Approved 04/15/2021
    25% Design 25% Package Received 12/08/2017
    25% Design 25% Package Comments to DE 04/06/2018
    25% Design 25% Package Approved 09/20/2019
    25% Design 25% Package Received - Resub 1 08/08/2019
    25% Design Design Public Hearing 06/27/2019
    75% Design 75% Package Received 02/14/2020
    Final Design PS&E Received 04/30/2021
    Final Design PS&E to FAPRO 06/14/2021
    Consultant Contract Process NTP Issued 12/16/2015
    Consultant Contract Process Workhours Approved 11/30/2015