Project Description:
WESTPORT- RESURFACING AND RELATED WORK ON ROUTE 88 FROM MILE MARKER 1.2 (JUST NORTH OF DRIFT ROAD) NORTHERLY TO MILE MARKER 7.5, JUST SOUTH OF OLD COUNTY ROAD
This is intended to be a pavement preservation project. The purpose is to improve rideability and safety. In addition, proposed related work includes cleaning of catch basins and installation of new catch basins and manholes. Install new guard rail. Remove and reset old guard rail. Remove and rest curbing. Selective clearing and thinning of vegetation along the roadside.
Location:
  • Town of Westport
  • Construction Begins: Summer 2017
    Resident Engineer: Matthew Pike
    Construction Bid Price: $3,897,164.25
    District: District 5

    Contracts (1) Progress
    # 99325 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 88 (Main Highway) and Adjacent Streets (Phase II) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/15/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/24/2014
    Project Initiation Form PIF Entered 10/24/2014
    Project Initiation Form PRC Submitted 10/28/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 12/17/2016
    Project Management
    100% Design 100% Package Received 10/19/2016
    100% Design 100% Package Comments to DE 11/02/2016
    25% Design 25% Package Received 01/25/2016
    25% Design 25% Package Comments to DE 03/03/2016
    25% Design 25% Package Approved 03/03/2016
    75% Design 75% Package Received 01/25/2016
    75% Design 75% Package Comments to DE 03/03/2016
    75% Design 75% Package Received - Resub 1 01/25/2016
    75% Design 75% Plans Approved 03/03/2016
    Final Design PS&E Received 10/19/2016
    Final Design PS&E to FAPRO 12/05/2016
    Final Design PS&E Received - Resub 1 11/10/2016
    Final Design PS&E Received - Resub 2 11/29/2016