Project Description:
AMHERST- IMPROVEMENTS & RELATED WORK ON ROUTES 9 & 116, FROM UNIVERSITY DRIVE TO SOUTH PLEASANT STREET (0.8 MILES)
This is a complete streets project that will improve accommodations for all users. The roadway will be resurfaced and widened for improved bicycle use with marked bicycle lanes, new and reconstructed sidewalks are proposed for improved pedestrian access, and new wheelchair ramps and crosswalks will be installed.
Location:
  • Town of Amherst
  • Construction Begins: Summer 2021
    Resident Engineer: Matthew Coughlin
    Construction Bid Price: $5,213,806.00
    District: District 2

    Contracts (2) Progress
    # 114418 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Northampton Road (Routes 9 & 116) 100% Complete
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/16/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/28/2014
    Project Initiation Form PIF Entered 10/28/2014
    Project Initiation Form PRC Submitted 10/29/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 04/24/2021
    Project Management
    100% Design 100% Package Received 04/30/2020
    100% Design 100% Package Comments to DE 07/28/2020
    25% Design 25% Package Received 10/06/2017
    25% Design 25% Package Comments to DE 01/25/2018
    25% Design 25% Package Received - Resub 1 10/25/2018
    25% Design Design Public Hearing 04/25/2019
    75% Design 75% Package Received 11/20/2019
    75% Design 75% Package Comments to DE 01/28/2020
    Final Design PS&E Received 12/21/2020
    Final Design PS&E Received - Resub 1 02/03/2021
    Final Design PS&E Received - Resub 2 04/01/2021
    Final Design PS&E Received - Resub 3 04/01/2021