Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
AVON- INSTALLATION OF A MEDIAN BARRIER ON HARRISON BOULEVARD
Work on this project consists of installing a median barrier on Harrison Boulevard between Pond Street and West Main Street.
Location:
  • Town of Avon
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Kenneth Belgrave
    Construction Bid Price: $2,224,238.71
    District: District 5

    Contracts (1) Progress
    # 96787 -- Construction Contract
    Resurfacing and Related Work (Including Median Barrier) along a Section of Harrison Boulevard. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/25/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/28/2014
    Project Initiation Form PIF Entered 10/28/2014
    Project Initiation Form PRC Submitted 10/28/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 08/06/2016
    Project Management
    100% Design 100% Package Received 03/03/2016
    25% Design 25% Package Received 11/16/2015
    25% Design 25% Package Comments to DE 12/14/2015
    75% Design 75% Package Received 11/16/2015
    75% Design 75% Package Comments to DE 12/14/2015
    Final Design PS&E Received 03/03/2016
    Final Design PS&E Received 04/28/2016
    Final Design PS&E to FAPRO 08/01/2016