Project Description:
AVON- INTERSECTION IMPROVEMENTS AT HARRISON BOULEVARD AND POND STREET
Work on this project consists of installing new traffic signal equipment, minor geometric improvements, and upgrading bicycle and pedestrian at the intersection.
Location:
  • Town of Avon
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Fedner Pierre
    Construction Bid Price: $3,998,824.70
    District: District 5
    Current Status: Cairns Completed all field work and punch list as of 9/6/2024. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM. (as of 09/26/2024)

    Contracts (2) Progress
    # 113931 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Harrison Boulevard at Pond Street Completed
    # 77851 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/18/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Cairns Completed all field work and punch list as of 9/6/2024. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/28/2014
    Project Initiation Form PIF Entered 10/28/2014
    Project Initiation Form PRC Submitted 10/28/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 01/30/2021
    Project Management
    100% Design 100% Package Received 11/01/2019
    100% Design 100% Package Comments to DE 01/02/2020
    25% Design 25% Package Received 12/16/2016
    25% Design 25% Package Comments to DE 05/24/2017
    25% Design 25% Package Received - Resub 1 02/22/2018
    25% Design Design Public Hearing 02/25/2019
    75% Design 75% Package Received 06/03/2019
    75% Design 75% Package Comments to DE 08/23/2019
    75% Design 75% Plans Approved 09/19/2019
    75% Design 75% Plans Complete 09/19/2019
    Final Design PS&E Received 06/19/2020
    Final Design PS&E Received - Resub 1 10/30/2020