Project Description:
BROCKTON- CORRIDOR IMPROVEMENTS ON ROUTE 123 (BELMONT STREET), FROM ANGUS BEATON DRIVE TO WEST STREET
Work on the project includes resurfacing and box cut widening along Route 123 to provide a consistent roadway cross seciton, bicycle accomodating sholders and accessible sidewalks. Traffic signals will be reconstructed to provide ADA accessible elements.
Location:
  • City of Brockton
  • Construction Begins: Autumn 2020
    Resident Engineer: Christopher Sera
    Construction Bid Price: $5,155,630.03
    District: District 5
    Current Status: 9/15/21 to 9/28/21: RW Bryant to complete relocation work for Comcast. Verizon to continue relocation work. Subcontractor Dagle to continue working on new traffic signals. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 09/14/2021)

    Contracts (3) Progress
    # 112084 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 123 (Belmont Street) 56% Complete
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/05/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    9/15/21 to 9/28/21: RW Bryant to complete relocation work for Comcast. Verizon to continue relocation work. Subcontractor Dagle to continue working on new traffic signals. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/28/2014
    Project Initiation Form PIF Entered 10/28/2014
    Project Initiation Form PRC Submitted 10/28/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 07/18/2020
    Project Management
    100% Design 100% Package Received 12/23/2019
    100% Design 100% Package Comments to DE 02/06/2020
    100% Design 100% Plans Approved 02/18/2020
    25% Design 25% Package Received 03/16/2017
    25% Design 25% Package Comments to DE 09/11/2017
    25% Design Design Public Hearing 04/25/2018
    75% Design 75% Package Received 01/08/2019
    75% Design 75% Package Comments to DE 04/12/2019
    Final Design PS&E Received 05/19/2020
    Final Design PS&E Received - Resub 1 06/19/2020
    Final Design PS&E Received - Resub 2 07/01/2020
    Final Design PS&E Received - Resub 3 07/01/2020