Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROCKTON- CORRIDOR IMPROVEMENTS ON ROUTE 123 (BELMONT STREET), FROM ANGUS BEATON DRIVE TO WEST STREET
Work on the project includes resurfacing and box cut widening along Route 123 to provide a consistent roadway cross seciton, bicycle accomodating sholders and accessible sidewalks. Traffic signals will be reconstructed to provide ADA accessible elements.
Location:
  • City of Brockton
  • Construction Begins: Autumn 2020
    Resident Engineer: Fedner Pierre
    Construction Bid Price: $5,155,630.03
    District: District 5
    Current Status: No work is scheduled. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 10/10/2024)

    Contracts (3) Progress
    # 112084 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 123 (Belmont Street) Completed
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87750 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 5. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/05/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    No work is scheduled. Normal work hours are Monday through Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/28/2014
    Project Initiation Form PIF Entered 10/28/2014
    Project Initiation Form PRC Submitted 10/28/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Status Advertised 07/18/2020
    Project Management
    100% Design 100% Package Received 12/23/2019
    100% Design 100% Package Comments to DE 02/06/2020
    100% Design 100% Plans Approved 02/18/2020
    25% Design 25% Package Received 03/16/2017
    25% Design 25% Package Comments to DE 09/11/2017
    25% Design Design Public Hearing 04/25/2018
    75% Design 75% Package Received 01/08/2019
    75% Design 75% Package Comments to DE 04/12/2019
    Final Design PS&E Received 05/19/2020
    Final Design PS&E Received - Resub 1 06/19/2020
    Final Design PS&E Received - Resub 2 07/01/2020
    Final Design PS&E Received - Resub 3 07/01/2020