Project Description:
WEYMOUTH- NEW ROADWAY CONNECTION BETWEEN TROTTER ROAD AND EAST WEST PARKWAY
As part of the southfield development, this new roadway will serve as a new connection between Trotter Road and the E-W Parkway
Location:
  • Town of Weymouth
  • Design Responsibility: Consultant
    Right of Way Responsibility: Other
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $7,758,602.15
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: PS&E Received (as of 01/26/2016 )

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64325 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/30/2014
    Project Initiation Form PIF Entered 10/30/2014
    Project Initiation Form PRC Submitted 11/03/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Management
    100% Design 100% Package Received 11/18/2015
    100% Design 100% Package Comments to DE 12/22/2015
    25% Design 25% Package Received 07/01/2015
    25% Design 25% Package Comments to DE 08/03/2015
    25% Design Design Public Hearing 10/07/2015
    75% Design 75% Package Received 11/18/2015
    75% Design 75% Package Comments to DE 12/22/2015
    Final Design PS&E Received 01/26/2016
    Consultant Contract Process Scope to DE 05/05/2015
    Consultant Contract Process NTP Issued 06/09/2015
    Consultant Contract Process Workhours Approved 05/27/2015