Project Description:
NORTH ANDOVER- CORRIDOR IMPROVEMENTS ON ROUTE 114, BETWEEN WAVERLY ROAD & WILLOW/MILL STREET
The project will upgrade traffic signals and improve safety along the corridor, install new signals at the Royal Crest Apartments and new access drive to Merrimack College, add sidewalks and formalize pedestrian crossings especially in the vicinity of Merrimack College, add turning lanes, bicycle accommodations and storm water treatment facilities.
Location:
  • Town of North Andover
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $39,449,081.54
    Estimated Total Federal Participating Construction Cost: $43,500,478.66
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: 75% Package Comments to DE (as of 08/26/2022 )

    Contracts (2) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ANDOVER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $34,083,859 STBG (inflated 4% from 2023 cost) = FFY 2024 ($5,495,380) + FFY 2025 ($13,239,974) + FFY 2026 ($12,916,056) + FFY 2027 ($2,432,449) c) AC years 1-4 FFY 2024-2027; d) TEC = 12.42 out of 18.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,687,167.20
    State Cost: $671,791.80
    Total Cost: $3,358,959.00

    Planned Federal FY: 2025
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ANDOVER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $34,083,859 STBG (inflated 4% from 2023 cost) = FFY 2024 ($5,495,380) + FFY 2025 ($13,239,974) + FFY 2026 ($12,916,056) + FFY 2027 ($2,432,449) c) AC years 1-4 FFY 2024-2027; d) TEC = 12.42 out of 18.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,053,733.30
    State Cost: $339,303.70
    Total Cost: $3,393,037.00

    Planned Federal FY: 2026
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ANDOVER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $34,083,859 STBG (inflated 4% from 2023 cost) = FFY 2024 ($5,495,380) + FFY 2025 ($13,239,974) + FFY 2026 ($12,916,056) + FFY 2027 ($2,432,449) c) AC years 1-4 FFY 2024-2027; d) TEC = 12.42 out of 18.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,259,680.00
    State Cost: $1,564,920.00
    Total Cost: $7,824,600.00

    Planned Federal FY: 2027
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ANDOVER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $34,083,859 STBG (inflated 4% from 2023 cost) = FFY 2024 ($5,495,380) + FFY 2025 ($13,239,974) + FFY 2026 ($12,916,056) + FFY 2027 ($2,432,449) c) AC years 1-4 FFY 2024-2027; d) TEC = 12.42 out of 18.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $8,592,552.80
    State Cost: $2,148,138.20
    Total Cost: $10,740,691.00

    Planned Federal FY: 2028
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: NORTH ANDOVER
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) $34,083,859 STBG (inflated 4% from 2023 cost) = FFY 2024 ($5,495,380) + FFY 2025 ($13,239,974) + FFY 2026 ($12,916,056) + FFY 2027 ($2,432,449) c) AC years 1-4 FFY 2024-2027; d) TEC = 12.42 out of 18.
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $10,857,719.20
    State Cost: $2,714,429.80
    Total Cost: $13,572,149.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/31/2014
    Project Initiation Form PIF Entered 10/31/2014
    Project Initiation Form PRC Submitted 10/31/2014
    Project Review Committee PRC Approved 11/06/2014
    Project Review Committee Resubmitted 02/11/2020
    Project Management
    25% Design 25% Package Received 07/29/2020
    25% Design 25% Package Comments to DE 11/13/2020
    25% Design Design Public Hearing 10/28/2021
    75% Design 75% Package Received 05/16/2022
    75% Design 75% Package Comments to DE 08/26/2022
    Consultant Contract Process NTP Issued 11/01/2016