Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEW BEDFORD- PARK AND RIDE IMPROVEMENTS INCLUDING A NEW BUS SHELTER REPLACEMENT AT THE MOUNT PLEASANT STREET PARK AND RIDE
Work will involve the removal and replacement of the bus shelter structures located within the New Bedford Park & Ride location. Base pads will be modified to meet current ADA/AAB standards.
Location:
  • City of New Bedford
  • Construction Begins: Autumn 2017
    Resident Engineer: Matthew Lambert
    Construction Bid Price: $377,881.35
    District: District 5

    Contracts (1) Progress
    # 100205 -- Construction Contract
    Resurfacing, Upgrades and Related Work (Including a New Bus Shelter) to the Park and Ride Lot at Mount Pleasant Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/20/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/03/2014
    Project Initiation Form PIF Entered 11/04/2014
    Project Initiation Form PRC Submitted 11/04/2014
    Project Review Committee PRC Approved 11/12/2014
    Project Status Advertised 04/15/2017
    Project Management
    100% Design 100% Package Received 12/22/2016
    75% Design 75% Package Received 09/27/2016
    Final Design PS&E Received 03/28/2017
    Final Design PS&E to FAPRO 03/28/2017
    Final Design PS&E Received - Resub 1 10/27/2017