Project Description:
WRENTHAM- BRIDGE PAINTING ON I-495 (NB & SB)
THIS CONTRACT WILL CONSIST OF CLEANING, PAINTING STEEL BRIDGES LISTED IN THIS CONTRACT
Location:
  • Town of Wrentham
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $2,166,691.75
    Construction Bid Price: $1,653,645.00
    Initial Construction Estimate: $2,198,000.00
    District: District 5

    Contracts (1) Progress
    # 86303 -- Construction Contract
    Cleaning and Painting of 5 Bridges Br. Nos. (W-46-008, W-46-010 (NB), W-46-010 (SB), W-46-011(SB) & W-46-011(NB)) along Interstate 495. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/10/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/12/2014
    Project Initiation Form PIF Entered 11/19/2014
    Project Initiation Form PRC Submitted 11/20/2014
    Project Review Committee PRC Approved 12/10/2014
    Project Status Advertised 01/10/2015
    Project Management
    75% Design 75% Package Received 12/10/2014
    Final Design PS&E Received 01/05/2015
    Final Design PS&E to FAPRO 01/06/2015