Project Description: |
DISTRICT 5- DISTRICT 6- SIGNAL UPGRADES WITH FLASHING YELLOW ARROWS AT VARIOUS LOCATIONS (PHASE II)
Upgrades include replacement of signal heads, controllers, etc and adding associated signage. Research has shown that upgrading to FYA will reduce the left turning crashes by 20%.
|
Location: | |
Resident Engineer: | Joseph Goncalves |
Construction Contract Value: | $676,028.51 |
Construction Bid Price: | $536,263.92 |
Initial Construction Estimate: | $568,000.00 |
District: | District 5 |
|