Project Description:
MIDDLEBOROUGH- INTERIM IMPROVEMENTS AT ROUTES 18/28/44 (ROTARY)
This project is intended to address ongoing safety and congestion issues on an interim basis. Proposed improvements include: striping of the rotary to a 2-lane facility; new signage, and geometric improvements at the access/egress points to/from the rotary.
Location:
  • Town of Middleborough
  • Construction Begins: Spring 2018
    Resident Engineer: Kenneth Belgrave
    Construction Bid Price: $1,111,104.25
    District: District 5

    Contracts (1) Progress
    # 102280 -- Construction Contract
    Resurfacing and Related Work including Roadway Realignment of Routes 18, 28 and 44 at the Rotary. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/18/2018
    Contract Information
    Project Designer:
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/17/2014
    Project Initiation Form PIF Entered 12/17/2014
    Project Initiation Form PRC Submitted 01/13/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 09/16/2017
    Project Management
    100% Design 100% Package Received 06/13/2017
    100% Design 100% Package Comments to DE 08/07/2017
    100% Design 100% Plans Approved 08/07/2017
    100% Design 100% Plans Complete 06/13/2017
    25% Design 25% Package Received 10/05/2015
    25% Design 25% Package Comments to DE 04/15/2016
    75% Design 75% Package Received 10/05/2015
    75% Design 75% Package Comments to DE 04/15/2016
    Final Design PS&E Received 08/28/2017
    Final Design PS&E to Peer Reviewer 08/28/2017
    Final Design Peer Review Comments to DE 09/01/2017
    Final Design PS&E to FAPRO 09/05/2017