Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- INTERIM IMPROVEMENTS AT CAMBRIDGE STREET & RIVER STREET
This project will provide upgrades to the traffic signals at the intersections of Cambridge Street/I-90 Ramps and River Street/Cambridge Street/Soldiers Field Road. Traffic signal timings and geometric improvements will increase capacity and enhance the safety of cyclists and pedestrians. ADA compliant ramps will be provided at the intersections, and a new cycle track will be installed along Soldiers Field Road between River Street and Western Avenue. New overhead vehicle indications will be included as well as pedestrian indications. In addition to these improvements, a new traffic signal controller and cabinet will be provided at River Street/Memorial Drive in order to maintain compatibility and communications.
Location:
  • City of Boston
  • Resident Engineer: Roderick Connelly III
    Construction Bid Price: $2,928,935.00
    District: District 6

    Contracts (2) Progress
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 87746 -- Construction Contract
    Interim Improvements along Cambridge – River Streets (Including Signals and Bridge Repairs (Br. No. B-16-377)) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/08/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/23/2014
    Project Initiation Form PIF Entered 12/23/2014
    Project Initiation Form PRC Submitted 12/23/2014
    Project Review Committee PRC Approved 02/23/2015
    Project Status Approved 25% 12/17/2014
    Project Status Advertised 04/11/2015
    Project Management
    100% Design 100% Package Received 12/17/2014
    Final Design PS&E Received 03/17/2015
    Final Design PS&E to FAPRO 04/08/2015