Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MANSFIELD- SWANSEA- SOMERSET- NEW BEDFORD- STORMWATER IMPROVEMENTS ALONG I-495 AND I-195
Stormwater improvements at various locations along I-495 and I-195 to treat discharges to Rumford River, New Bedford Inner Harbor and Lee River.
Location:
  • Town of Mansfield
  • City of New Bedford
  • Town of Somerset
  • Town of Swansea
  • Resident Engineer: Marc Cardinal
    Construction Bid Price: $1,609,212.50
    District: District 5

    Contracts (1) Progress
    # 90709 -- Construction Contract
    Drainage Repairs along Sections of Route 103 (Wilbur Avenue) and Interstates 195 & 495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/13/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/02/2015
    Project Initiation Form PIF Entered 01/02/2015
    Project Initiation Form PRC Submitted 01/02/2015
    Project Review Committee PRC Approved 03/05/2015
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 06/29/2015
    100% Design 100% Package Comments to DE 08/06/2015
    75% Design 75% Package Received 01/11/2013
    75% Design 75% Package Received 08/20/2013
    75% Design 75% Package Received 01/29/2014
    75% Design 75% Package Comments to DE 02/04/2015
    Final Design PS&E Received 09/08/2015
    Final Design PS&E Received 09/25/2015
    Final Design PS&E to Peer Reviewer 08/19/2015
    Final Design Peer Review Comments to DE 09/04/2015
    Final Design PS&E to FAPRO 09/11/2015