Project Description:
OAK BLUFFS- CONSTRUCTION OF A SHARED USE PATH ALONG BEACH ROAD, FROM THE LAGOON POND BRIDGE NORTHERLY TO THE EASTVILLE AVENUE/COUNTY ROAD INTERSECTION
This project is intended to create a new shared use path extending from the reconstructed Lagoon Pond Bridge on Beach Road Northerly onto Eastville Road. The path would terminate at County Road, connecting to an existing shared use path.
Location:
  • Town of Oak Bluffs
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Michael King
    Construction Bid Price: $3,967,860.07
    District: District 5
    Current Status: Operations are currently secured with the intent to resume construction operations on 4/24/24. Pending operations include drainage structure cleaning, sign placements and landscape corrective actions. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. (as of 04/17/2024)

    Contracts (2) Progress
    # 116294 -- Construction Contract
    Construction of a Shared Use Path along a Section of Beach Road 98% Complete
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/05/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Operations are currently secured with the intent to resume construction operations on 4/24/24. Pending operations include drainage structure cleaning, sign placements and landscape corrective actions. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/14/2015
    Project Initiation Form PIF Entered 04/21/2016
    Project Initiation Form PRC Submitted 05/23/2016
    Project Review Committee PRC Approved 06/09/2016
    Project Status Advertised 09/11/2021
    Project Management
    100% Design 100% Package Received 11/16/2020
    100% Design 100% Package Comments to DE 12/21/2020
    25% Design 25% Package Received 06/29/2018
    25% Design 25% Package Comments to DE 11/02/2018
    25% Design Design Public Hearing 10/29/2019
    75% Design 75% Package Received 02/18/2020
    75% Design 75% Package Comments to DE 05/06/2020
    75% Design 75% Plans Approved 02/06/2020
    Final Design PS&E Received 05/03/2021
    Final Design PS&E to FAPRO 08/27/2021