Project Description:
ABINGTON- BROCKTON- INTERSECTION IMPROVEMENTS AT NORTH QUINCY STREET, BOUNDARY AVENUE AND CHESTNUT STREET
The intent of this project is to address a high crash location by implementing intersection improvements and improved pedestrian and bicycle accommodations.
Location:
  • Town of Abington
  • City of Brockton
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Christopher Sera
    Construction Bid Price: $1,934,219.50
    District: District 5
    Current Status: 8/24/21 to 9/24/21: Contractor will water plantings, perform any punch list work, and demobilize from project. Normal work hours are Monday thru Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 08/24/2021)

    Contracts (1) Progress
    # 109529 -- Construction Contract
    Intersection Improvements and Related Work North Quincy Street at Boundary Avenue and Chestnut Street Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/14/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    8/24/21 to 9/24/21: Contractor will water plantings, perform any punch list work, and demobilize from project. Normal work hours are Monday thru Friday 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/14/2015
    Project Initiation Form PIF Entered 02/13/2015
    Project Initiation Form PRC Submitted 02/18/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 08/31/2019
    Project Management
    100% Design 100% Package Received 11/02/2018
    100% Design 100% Package Comments to DE 12/11/2018
    25% Design 25% Package Received 09/06/2016
    25% Design 25% Package Comments to DE 01/24/2017
    25% Design Design Public Hearing 01/30/2018
    75% Design 75% Package Received 07/03/2018
    75% Design 75% Package Comments to DE 09/04/2018
    Final Design PS&E Received 06/04/2019
    Final Design PS&E Received - Resub 1 08/07/2019