MARBLEHEAD- INTERSECTION IMPROVEMENTS AT PLEASANT STREET & VILLAGE, VINE AND CROSS STREETS
The intersection improvements will include realignment of Vine Street to form a "T" intersection, narrowing and realigning Pleasant Street to minimize crossing distance, the installation of new sidewalk, signs, enhanced lighting, modest drainage modifications as well as ADA/AAB crossing enhancements and shared bicycle accommodations. The length of the project involves approximately 800 linear feet—400 linear feet on Pleasant Street (200 feet east and west of the intersection), 150 linear feet on Village Street, 150 linear feet on Vine Street, and 100 linear feet on Cross Street. Drainage and utility adjustments will be made as needed to accommodate the proposed intersection channelization modifications.
Location:
  • Town of Marblehead
  • Construction Begins: Autumn 2021
    Resident Engineer: Carmen Ilardi
    Construction Bid Price: $772,995.75
    District: District 4

    Contracts (1) Progress
    # 115833 -- Construction Contract
    Intersection Improvements and Related Work Pleasant Street at Cross, Village and Vine Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/08/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/16/2015
    Project Initiation Form PIF Entered 01/16/2015
    Project Initiation Form PRC Submitted 02/18/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 08/07/2021
    Project Management
    100% Design 100% Package Received 04/30/2021
    25% Design 25% Package Received 03/16/2017
    25% Design 25% Package Received 01/07/2020
    25% Design 25% Package Comments to DE 06/26/2020
    25% Design 25% Package Received - Resub 1 12/16/2019
    25% Design 25% Package Received - Resub 2 06/29/2020
    25% Design Design Public Hearing 06/16/2020
    75% Design 75% Package Received 11/05/2020
    75% Design 75% Package Received 01/12/2021
    75% Design 75% Package Comments to DE 02/15/2021
    Final Design PS&E Received 07/16/2021
    Final Design PS&E to FAPRO 07/26/2021