Project Description:
NORTH ATTLEBOROUGH- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
Interstate maintenance pavement preservation resurfacing, safety improvements and related work from MM 8.2 to MM 9.4 for a total project length of 1.2 centerline miles.
Location:
  • Town of North Attleborough
  • Construction Begins: Spring 2016
    Resident Engineer: Brian Lewis
    Construction Bid Price: $1,597,428.60
    District: District 5

    Contracts (1) Progress
    # 92541 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 95. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/04/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/21/2015
    Project Initiation Form PIF Entered 01/21/2015
    Project Initiation Form PRC Submitted 01/21/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 12/26/2015
    Project Management
    100% Design 100% Package Received 11/25/2015
    25% Design 25% Package Received 10/01/2015
    25% Design 25% Package Comments to DE 11/06/2015
    75% Design 75% Package Received 10/01/2015
    75% Design 75% Package Comments to DE 11/06/2015
    Final Design PS&E Received 11/25/2015
    Final Design PS&E to FAPRO 12/21/2015