Project Description:
WESTWOOD- NORWOOD- RECONSTRUCTION OF CANTON STREET TO UNIVERSITY DRIVE, INCLUDING REHAB OF N-25-032=W-31-018
This project extends along Canton Street for 1.9 miles, between the East Street Rotary and University Avenue in the Town of Westwood, and partially abutting the Town of Norwood. One purpose of this project is to provide traffic calming along the corridor through the reconstruction of strategically placed raised median islands, which will also serve as pedestrian refuge at crosswalk locations. Pedestrians and bicyclists will be accommodated to the maximum extent practicable through the construction of an 8 to 10 foot wide shared-use path along the east side of Canton Street and a 5.5 foot wide sidewalk along the west side. The bridge (N-25-032=W-31-018) carrying Canton Street over the railroad tracks approximately 450 feet north of the University Avenue intersection will be rehabilitated and resurfaced to accommodate the shared-use path. Minor modifications will be made to the existing signalized intersection at University Avenue. This corridor serves as a vital connection between residences, the mixed-use commercial district along University Avenue, and the Route 128/University Park Commuter Rail Station. Pedestrians and cyclists may also use the proposed infrastructure to access the Downey School, which is located approximately ½ mile to the southwest via Downey Street.
Location:
  • Town of Norwood
  • Town of Westwood
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2028
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $18,195,004.88
    Estimated Total Federal Participating Construction Cost: $20,406,112.91
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: Design Public Hearing (as of 09/28/2023 )

    Contracts (1) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NORWOOD
    WESTWOOD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $3,200,000.00
    State Cost: $800,000.00
    Total Cost: $4,000,000.00

    Planned Federal FY: 2028
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NORWOOD
    WESTWOOD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $7,083,877.60
    State Cost: $1,770,969.40
    Total Cost: $8,854,847.00

    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NORWOOD
    WESTWOOD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $8,000,000.00
    State Cost: $2,000,000.00
    Total Cost: $10,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/04/2015
    Project Initiation Form PIF Entered 02/04/2015
    Project Initiation Form PRC Submitted 02/04/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Management
    25% Design 25% Package Received 02/18/2022
    25% Design 25% Package Comments to DE 05/31/2022
    25% Design Design Public Hearing 09/28/2023