Project Description:
WALES- RECONSTRUCTION & IMPROVEMENTS ON MONSON ROAD, FROM THE MONSON T.L. TO REED HILL ROAD (1.5 MILES)
This project will consist of roadway reclamation and pavement widening. The existing pavement will be widened for usable shoulder and improved bicycle accommodations, drainage deficiencies will be repaired, intersection and sight distance improvements, new signage and pavement markings.
Location:
  • Town of Wales
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2024/2025
    Project Manager: Kimberley Sloan
    Estimated Total Contract Cost: $13,928,180.55
    Estimated Total Federal Participating Construction Cost: $15,301,422.59
    District: District 2
    Current Status: This project has been advertised for construction bids. (as of 09/14/2024 )

    Contracts (1) Progress
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/19/2015
    Project Initiation Form PIF Entered 02/19/2015
    Project Initiation Form PRC Submitted 02/26/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 09/14/2024
    Project Management
    100% Design 100% Package Received 04/18/2024
    100% Design 100% Package Comments to DE 05/20/2024
    25% Design 25% Package Received 03/01/2018
    25% Design 25% Package Comments to DE 05/28/2019
    25% Design 25% Package Received - Resub 1 10/24/2018
    25% Design Design Public Hearing 09/19/2019
    75% Design 75% Package Received 06/17/2020
    75% Design 75% Package Comments to DE 09/21/2020
    75% Design 75% Package Received - Resub 1 11/20/2023
    75% Design 75% Package Received - Resub 2 01/09/2024
    Final Design PS&E Received 08/22/2024
    Final Design PS&E to FAPRO 08/30/2024