Project Description: |
WALES- RECONSTRUCTION & IMPROVEMENTS ON MONSON ROAD, FROM THE MONSON T.L. TO REED HILL ROAD (1.5 MILES)
This project will consist of roadway reclamation and pavement widening. The existing pavement will be widened for usable shoulder and improved bicycle accommodations, drainage deficiencies will be repaired, intersection and sight distance improvements, new signage and pavement markings.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Construction Begins: | Autumn 2024 |
Project Manager: | Shawn Holland![]() |
Estimated Total Contract Cost: | $4,598,343.00 |
Estimated Total Federal Participating Construction Cost: | $5,438,563.26 |
Funding Provision: | This project is planned to be funded through the 2024 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization. |
District: | District 2 |
Current Status: | 75% Package Comments to DE (as of 09/21/2020 ) |
|
Bridges |
|
|
|