WALES- RECONSTRUCTION & IMPROVEMENTS ON MONSON ROAD, FROM THE MONSON T.L. TO REED HILL ROAD (1.5 MILES)
This project will consist of roadway reclamation and pavement widening. The existing pavement will be widened for usable shoulder and improved bicycle accommodations, drainage deficiencies will be repaired, intersection and sight distance improvements, new signage and pavement markings.
Location:
  • Town of Wales
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2024
    Project Manager: Shawn Holland
    Estimated Total Contract Cost: $4,598,343.00
    Estimated Total Federal Participating Construction Cost: $5,438,563.26
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 75% Package Comments to DE (as of 09/21/2020 )

    Contracts (1) Progress
    # 115801 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WALES
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction / YOE $5,656,106 / 39.5 TEC / 75% STBG
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,524,884.80
    State Cost: $1,131,221.20
    Total Cost: $5,656,106.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/19/2015
    Project Initiation Form PIF Entered 02/19/2015
    Project Initiation Form PRC Submitted 02/26/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Management
    25% Design 25% Package Received 03/01/2018
    25% Design 25% Package Comments to DE 05/28/2019
    25% Design 25% Package Received - Resub 1 10/24/2018
    25% Design Design Public Hearing 09/19/2019
    75% Design 75% Package Received 06/17/2020
    75% Design 75% Package Comments to DE 09/21/2020