Project Description:
SUDBURY- CONCORD- BIKE PATH CONSTRUCTION (BRUCE FREEMAN RAIL TRAIL)
The proposed project involves construction of a 5.1 mile trail in Sudbury and Concord, from Powder Mill Road in Concord to Station Road in Sudbury. The proposed work includes improvements to two structures, as well as upgrades to several at-grade crossings including Route 117 (North Road), Pantry Road, and Route 27 (Hudson Road). Related work includes pavement markings, installation of guardrail and landscaping.
Location:
  • Town of Concord
  • Town of Sudbury
  • Construction Begins: Autumn 2022
    Resident Engineer: Adam Nabulsi
    Construction Bid Price: $10,518,738.00
    District: District 3

    Contracts (1) Progress
    # 119678 -- Construction Contract
    Construction of the Bruce Freeman Rail Trail Including Signals and 2 Bridges (Phase 2D) 85% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 10/13/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/19/2015
    Project Initiation Form PIF Entered 02/19/2015
    Project Initiation Form PRC Submitted 03/02/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 08/06/2022
    Project Management
    100% Design 100% Package Received 01/18/2022
    100% Design 100% Package Comments to DE 03/07/2022
    25% Design 25% Package Received 09/18/2017
    25% Design 25% Package Comments to DE 09/06/2018
    25% Design Design Public Hearing 07/16/2020
    75% Design 75% Package Received 05/12/2021
    75% Design 75% Package Comments to DE 07/08/2021
    Final Design PS&E Received 05/18/2022
    Final Design PS&E Received - Resub 1 06/28/2022