Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CLARKSBURG- RESURFACING AND RELATED WORK ON ROUTE 8, FROM THE NORTH ADAMS T.L. TO THE VERMONT S.L.
This project consists of resurfacing and related work on Route 8 from the North Adams/Clarksburg line (MM 63.99) to the Vermont State line (MM 66.73).
Location:
  • Town of Clarksburg
  • Construction Begins: Autumn 2017
    Resident Engineer: Christopher Pompi
    Construction Bid Price: $3,056,462.10
    District: District 1

    Contracts (1) Progress
    # 100228 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 8 (River Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/01/2017
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/23/2015
    Project Initiation Form PIF Entered 02/23/2015
    Project Initiation Form PRC Submitted 02/23/2015
    Project Review Committee PRC Approved 03/19/2015
    Project Status Advertised 04/22/2017
    Project Management
    100% Design 100% Package Received 03/27/2017
    25% Design 25% Package Received 01/04/2017
    25% Design 25% Package Comments to DE 01/18/2017
    75% Design 75% Package Received 01/04/2017
    75% Design 75% Package Comments to DE 01/18/2017
    Final Design PS&E Received 03/27/2017
    Final Design PS&E to FAPRO 04/10/2017