UXBRIDGE- RECONSTRUCTION OF ROUTE 122 (SOUTH MAIN STREET), FROM SUSAN PARKWAY TO ROUTE 16
The proposed improvements include a combination of roadway reconstruction and resurfacing, sidewalk construction or reconstruction and upgrade or installation of drainage structures.
Location:
  • Town of Uxbridge
  • Design Responsibility: Consultant
    Project Manager: Janhavi Limaye
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: PS&E Received - Resub 3 (as of 06/06/2024 )

    Contracts (4) Progress
    # 115748 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 117074 -- Design -- Services
    Work will generally involve the collection of electronic field survey data and the completion of AutoCAD Base Plans for general highway and bridge projects throughout the stat Final
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86789 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2015
    Project Initiation Form PIF Entered 03/02/2015
    Project Initiation Form PRC Submitted 03/02/2015
    Project Review Committee PRC Approved 03/03/2015
    Project Management
    100% Design 100% Package Received 01/12/2022
    100% Design 100% Package Comments to DE 03/17/2022
    100% Design 100% Package Received - Resub 1 07/27/2023
    25% Design Design Public Hearing 11/09/2022
    75% Design 75% Package Received 04/08/2015
    75% Design 75% Package Comments to DE 11/23/2016
    Final Design PS&E Received 03/29/2024
    Final Design PS&E Received - Resub 1 04/11/2024
    Final Design PS&E Received - Resub 2 05/13/2024